Refurbishment

Location: Sydney
Client: Target

The Solution

Management of building approvals and alternate solutions.

Alternative D&C services design on hydraulic services and electrical to ensure budgets could be maintained.

Construction of new café and associated services.

80% of works completed at night to ensure minimal disruption to trading.

Management and coordination of target supplied items.

Completion Date

Week Turnaround

Photo Gallery

What our customers say

Find out what our customers had to say about their experience working with us.

“We were really impressed with Girvan Waugh’s commitment and professionalism in getting the job done. They went above and beyond to finish the project in an 8 week programme – a first for Target, with the usual programme lasting 14 weeks.”

Jacques Steyn

Former NSW State Construction Manager - Store Development, Target